How to Import a Microsoft Project Schedule into Primavera With Same dates

Updated: May 17, 2018

Let us now learn How to Import a Microsoft Project Schedule into Primavera with the same dates exiting in the Microsoft project

Primavera have the option of Importing the schedules which are in the following formats.



If we directly import from Microsoft project in the .MPP format by default. The dates may differ from the Microsoft Project when the calendars in the two formats are different. So, as to eradicate this issue, there is a best way of importing. It is simple. First we have to convert the MSP file to .XML format and then import the .xml  format in to primavera and see that the dates don't get changed.

It is a very helpful tool for those who work on two platforms.


Step 1:

Open the Schedule in the Microsoft Project and save it in the Microsoft .XML format.