Hi, Lets see How we can change the Calendar once the schedule is prepared.

As per the Scheduling Philosophy, Calendar has to be set before beginning the schedule preparation.


To set the Default calendar,

Step 1:

Go to Enterprise>>Calendars,



Step 2:

Tick the Calendar which you want to make it default,


Step 3:

If you want to further change the timings and work weeks, click on Modify


Step 4:

Click on Work Weeks and Change the Time periods for the work hours in the default calendar



Step 5:

After Creating th Schedule, in the middle of the schedule, if you want to change the calendar  for the activities that you enter further, Go to Details tab>>Defaults Tab;It will show the default calendar, if you want to change the calendar, select the calendar clicking the bubble.